Corporation of the Town of Collingwood (Canada)
RE: Town of Collingwood - Master Stormwater Management Final Report
Your team did a great job conveying the output of your work to the Development Committee last night. I think the analysis was well understood by Members, and that there is confidence in the approach you have taken to the work. This topic is very important for Collingwood, and it is great to have this intelligent analysis from which to continue to leap forward.
Sincerely,
Sonya G. Skinner, P. Eng.
Chief Administrative Officer
Corporation of the Town of Collingwood (Canada)
February 15, 2022
The City of Waterloo
As a Senior Project Engineer (Water Resources) for the City of Waterloo, I would like to extend my appreciation to Greenland Consulting Engineers for providing exemplary EA planning, design, contract administration and construction inspection services for the Pond #53 Sediment Removal/Reuse and Retrofit Project.
This project was an important undertaking for the City which consisted of: the removal of 360m3 of sediment for reuse in a City owned boulevard area; removal of all additional sediment (approx. 3,000m3) from the SWMF permanent pool and forebay area to improve its operation, implementation of the retrofit design including improved maintenance access and proactive management of many unforeseen conditions throughout the duration of the project. This project also included significant logistical challenges with respect to the coordination of public access for area residents and businesses, and providing workable solutions to implementing the design as intended due to challenging unforseen site constraints.
As the Design Consultant, Contract Administrator and on-site Construction Inspector, Greenland always maintained open lines of communication between the City, Contractor and the affected residents, and promptly responded to all questions and issues raised by the Contractor, the City and the public. Greenland’s attention to detail throughout the entire duration of this assignment helped ensure the project was completed as required.
Jessica Kellerman, P. Eng
Senior Project Engineer - Water Resources
Engineering Services, Design & Construction
City of Waterloo
October 24, 2019
Town of Penetanguishene
As Director of Public Works for the Town of Penetanguishene, I would like to extend my appreciation to Greeland Consulting Engineers for providing exemplary contract administration and construction inspection services for the Penetang Main Street Reconstruction Project.
The Main Street reconstruction was a huge undertaking for the Town which consisted of: the full reconstruction of 1.4 km of roadway including widening for improved land widths, on-street parking, storm sewer replacement, watermain and sanitary sewer replacement, as well as landscaping and lighting improvements to better serve businesses and residents. The project included significant logistical challenges with respect to the coordination of public access for businesses, and providing workable upgrades to exisiting infrastructure under difficult site constraints and a tight time line.
As the Contract Administrator and on-site Construction inspector, Greenland always maintained open lines of communication between the Town, Contractor, affected businesses and residents, and promptly, responded to all questions and issues raised by the Contractor, the Town and the public. Greeland's attention to detail throughout the assignment helped ensure the project was completed on-time and under budget.
Bryan Murray, P. Eng
Director of Public Works
Town of Penetanguishene
February 12, 2019